Skip to main content.

UK Research & Innovation: UKRI-2253 R80 Tower Decommissioning and Adiabatic Cooler Design and Build

  UK Research & Innovation is using Delta eSourcing to run this tender exercise

Notice Summary
Title: UKRI-2253 R80 Tower Decommissioning and Adiabatic Cooler Design and Build
Notice type: Contract Notice
Authority: UK Research & Innovation
Nature of contract: Works
Procedure: Open
Short Description: UKRI wishes to establish a Contract for the provision of R80 Tower Decommissioning and Adiabatic Cooler Design and Build. The estimated value of this opportunity is £1,000,000 - £2,000,000. The scope includes management and delivery of design and construction services for the R80 Chilled water and process systems at the site address Rutherford Appleton Laboratory, Harwell, Oxford, Didcot OX11 0QX. The Contractor is required to act as a design and build contractor and will be responsible for all civil, mechanical, electrical construction; installation and commissioning within the CDM Works area.
Published: 15/08/2022 16:05

View Full Notice

UK-Swindon: Installation work of cooling equipment.
Section I: Contracting Authority
      I.1) Name and addresses
             UK Research & Innovation
             Polaris House, North Star Avenue, Swindon, Swindon, SN2 1FL, United Kingdom
             Tel. +44 1235446553, Email: procurement@stfc.ac.uk
             Contact: STFC Procurement
             Main Address: https://www.ukri.org
             NUTS Code: UK
      I.2) Joint procurement
      The contract involves joint procurement: No.
      In the case of joint procurement involving different countries, state applicable national procurement law: Not provided       
      The contract is awarded by a central purchasing body: No.
      I.3) Communication
      The procurement documents are available for unrestricted and full direct access, free of charge, at: https://www.delta-esourcing.com/tenders/UK-UK-Swindon:-Installation-work-of-cooling-equipment./5YQ64BANP4
      Additional information can be obtained from: the abovementioned address
      Tenders or requests to participate must be sent to the abovementioned address       
      Electronic communication requires the use of tools and devices that are not generally available. Unrestricted and full direct access to these tools and devices is possible, free of charge, at: Not provided
      I.4) Type of the contracting authority
            Body governed by public law
      I.5) Main activity
            Other activity:

Section II: Object
II.1) Scope of the procurement
      II.1.1) Title: UKRI-2253 R80 Tower Decommissioning and Adiabatic Cooler Design and Build       
      Reference Number: UKRI-2253
      II.1.2) Main CPV Code:
      45331230 - Installation work of cooling equipment.

      II.1.3) Type of contract: WORKS
      II.1.4) Short description: UKRI wishes to establish a Contract for the provision of R80 Tower Decommissioning and Adiabatic Cooler Design and Build. The estimated value of this opportunity is £1,000,000 - £2,000,000. The scope includes management and delivery of design and construction services for the R80 Chilled water and process systems at the site address Rutherford Appleton Laboratory, Harwell, Oxford, Didcot OX11 0QX.
The Contractor is required to act as a design and build contractor and will be responsible for all civil, mechanical, electrical construction; installation and commissioning within the CDM Works area.       
      II.1.5) Estimated total value:
      Value excluding VAT: 2,000,000       
      Currency: GBP
      II.1.6) Information about lots:
      This contract is divided into lots: No       
   
II.2) Description
      
      II.2.2) Additional CPV codes:
      42500000 - Cooling and ventilation equipment.
      
      II.2.3) Place of performance:
      UK UNITED KINGDOM
      
      II.2.4) Description of procurement: The Contractor is required to act as a design and build contractor and will be responsible for all civil, mechanical, electrical construction; installation and commissioning of the following – but not limited to - within the CDM Works area (i.e., The R80 roof area) and in accordance with the Completion Dates (See Provisional Programme within Appendix D - Project Brief).

- 8 No New Adiabatic coolers (AC’s).
- Connecting pipework and fittings to and the new AC’s within the CDM Works Area.
- All types of valves (isolation, regulating, non-return either manual or actuated).
- Commissioning sets and pressure reducing valves.
- Testing and drainage points.
- Basket and other Filters.
- All steel support work for the Adiabatic Coolers.
- All pipework supports.
- All local electrical power and signal cabling with cable trays etc and supports.
- All necessary civil surveying /setting out work.

The Contractor will be entirely responsible for organising the decommissioning and removal of the existing Balticare Cooling Towers within the CDM Works Area.

Background
The ISIS Neutron and Muon Source is a world-leading centre for research at the STFC Rutherford Appleton Laboratory near Oxford. The R80 facility houses the Second Target Station (TS2) and its associated neutron beamlines. At the end of each beam line is an instrument hut complete with research instrumentation all of which require a source of suitably graded cold demineralised water. The Demin cooling water used to cool the target is provided by a ‘closed loop’ circuit with the duty/standby pump arrangement; two Plate Heat Exchangers (PHExs) and associated controls situated within the Level 2 West Plant Area T222. Likewise, the instrument water is fed from a similar set up situated within the Level 2 West Plant Area T220 on the same storey. A source of cooling is also necessary for the focusing magnets and associated power supplies along the main proton beamline that leads to TS2 - known as the Extract Proton Beamline 2 or EPB2. The R6 Plant link room – situated in the corridor that links the R6 facility to R80 – houses the EPB2 Magnet Demin cooling water system and a separate power supplies Demin circuit. All the above ‘closed loop’ water circuits contain a ‘coarse’ grade cooling PHEx that uses the process water (PW) and a PHEx fed with chilled water (CHW) used to ‘trim’ each circuit Demin to the required Semin water supply temperature.

Currently the process water circuit is a ‘closed circuit’ system comprising of 5 No Balticare (BAC) VX1-180-4+XB towers each rated at 800 kW. These towers are located on the R80 4th floor roof. Adjacent to the roof area leading to the first two towers is the R80 Chilled Water Plant room (Level 4 West plant room T410) which houses both the duty/standby process water pumps and 3 No TRANE 850 kW R134a charged RTHD C2 D5 E4 Chillers which are water cooled using the PW. Flow is maintained through the packaged chillers and primary loop header system by duty/standby chilled water pumps located within the Level 2 West plan room T222 together with the target circuit. Besides providing cooling to the different CHW PHExs mentioned above the chilled water system also provides substantial space cooling via Fan Coil Units (FCUs) situated in the R80 office; laboratories; server and control rooms.

The water circuits were originally designed and installed by HADEN-YOUNG during the original construction phase of the R80 facility in 2006.
      II.2.5) Award criteria:
            Price is not the only award criterion and all criteria are stated only in the procurement documents            
      II.2.6) Estimated value:
      Value excluding VAT: 2,000,000       
      Currency: GBP       
      II.2.7) Duration of the contract, framework agreement or dynamic purchasing system:
      Duration in months: 32       
      This contract is subject to renewal: No       
      Description of renewals: Not provided
      
      II.2.10) Information about variants:
      Variants will be accepted: No
      II.2.11) Information about options:
      Options:       No             
      Description of options: Not provided
      II.2.12) Information about electronic catalogues:
      Tenders must be presented in the form of electronic catalogues or include an electronic catalogue: No
      II.2.13) Information about European Union funds:
      The procurement is related to a project and/or programme financed by European Union funds: No       
      Identification of the project: Not provided             
      II.2.14) Additional information: Additional information: We strongly recommend that you attend the Site Tour in order to gain complete clarity of our requirements. Please follow the instructions within the ITT.       


Section III: Legal, Economic, Financial And Technical Information
   III.1) Conditions for participation
      III.1.1) Suitability to pursue the professional activity, including requirements relating to enrolment on professional or trade registers
      List and brief description of conditions:          
      Not Provided       
      III.1.2) Economic and financial standing       
      List and brief description of selection criteria:       
      Not Provided    
      Minimum level(s) of standards possibly required (if applicable) :       
      Not Provided    
      III.1.3) Technical and professional ability
      List and brief description of selection criteria:       
      Not Provided      
      Minimum level(s) of standards possibly required (if applicable) :          
      Not Provided   
      III.1.5) Information about reserved contracts (if applicable)   
      The contract is reserved to sheltered workshops and economic operators aiming at the social and professional integration of disabled or disadvantaged persons: No       
      The execution of the contract is restricted to the framework of sheltered employment programmes: No    
      
   III.2) Conditions related to the contract
         
      III.2.2) Contract performance conditions          
      Not Provided          
      III.2.3) Information about staff responsible for the performance of the contract
      Obligation to indicate the names and professional qualifications of the staff assigned to performing the contract: No

Section IV: Procedure
   IV.1) Description OPEN
      IV.1.1) Type of procedure: Open   
   
   IV.1.3) Information about a framework agreement or a dynamic purchasing system    
         The procurement involves the establishment of a framework agreement - NO    
         In the case of framework agreements justification for any duration exceeding 4 years: Not Provided    
   
   
   IV.1.6) Information about electronic auction:
      An electronic auction will be used: No
      Additional information about electronic auction: Not provided
   IV.1.8) Information about the Government Procurement Agreement (GPA)
      The procurement is covered by the Government Procurement Agreement: Yes       
   IV.2) Administrative information
      IV.2.1) Previous publication concerning this procedure:
         Notice number in the OJ S: Not provided       
      IV.2.2) Time limit for receipt of tenders or requests to participate
       Date: 30/09/2022 Time: 14:00
            
      IV.2.4) Languages in which tenders or requests to participate may be submitted: English,       
      IV.2.6) Minimum time frame during which the tenderer must maintain the tender:
         Duration in month(s): 3
      
      IV.2.7) Conditions for opening of tenders:
         Date: 30/09/2022
         Time: 14:00
      

Section VI: Complementary Information
   VI.1) Information about recurrence
   This is a recurrent procurement: No    
   Estimated timing for further notices to be published: Not provided
   VI.2) Information about electronic workflows
   Electronic ordering will be used No       
   Electronic invoicing will be accepted Yes       
   Electronic payment will be used No       
   VI.3) Additional Information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.
For more information about this opportunity, please visit the Delta eSourcing portal at:
https://ukri.delta-esourcing.com/tenders/UK-UK-Swindon:-Installation-work-of-cooling-equipment./5YQ64BANP4

To respond to this opportunity, please click here:
https://ukri.delta-esourcing.com/respond/5YQ64BANP4
   VI.4) Procedures for review
   VI.4.1) Review body:
             UK Research and Innovation
       Swindon, United Kingdom
   VI.4.2) Body responsible for mediation procedures:
Not provided
   VI.4.3) Review procedure
   Precise information on deadline(s) for review procedures:    
    Not Provided    
   VI.4.4) Service from which information about the lodging of appeals may be obtained:
Not provided
   VI.5) Date Of Dispatch Of This Notice: 15/08/2022

Annex A


View any Notice Addenda

View Award Notice

UK-Swindon: Installation work of cooling equipment.

Section I: Contracting Authority

   I.1) Name, Addresses and Contact Point(s):
       UK Research & Innovation
       Polaris House, North Star Avenue, Swindon, Swindon, SN2 1FL, United Kingdom
       Tel. +44 1235446553, Email: procurement@stfc.ac.uk
       Contact: STFC Procurement
       Main Address: https://www.ukri.org
       NUTS Code: UK

   I.2) Joint procurement:
      The contract involves joint procurement: No          
      In the case of joint procurement involving different countries, state applicable national procurement law: Not Provided
      The contract is awarded by a central purchasing body: No

   I.4)Type of the contracting authority:
      Body governed by public law

   I.5) Main activity:
      Other activity: Research and Innovation

Section II: Object Of The Contract

   II.1) Scope of the procurement

      II.1.1) Title: UKRI-2253 R80 Tower Decommissioning and Adiabatic Cooler Design and Build            
      Reference number: UKRI-2253

      II.1.2) Main CPV code:
         45331230 - Installation work of cooling equipment.


      II.1.3) Type of contract: WORKS

      II.1.4) Short description: UKRI wishes to establish a Contract for the provision of R80 Tower Decommissioning and Adiabatic Cooler Design and Build. The estimated value of this opportunity is £1,000,000 - £2,000,000. The scope includes management and delivery of design and construction services for the R80 Chilled water and process systems at the site address Rutherford Appleton Laboratory, Harwell, Oxford, Didcot OX11 0QX. The Contractor is required to act as a design and build contractor and will be responsible for all civil, mechanical, electrical construction; installation and commissioning within the CDM Works area.

      II.1.6) Information about lots
         This contract is divided into lots: No
            
      II.1.7) Total value of the procurement (excluding VAT)
          Value: 1,507,366
                  
         Currency:GBP            

   II.2) Description

      II.2.2) Additional CPV code(s):
            42500000 - Cooling and ventilation equipment.


      II.2.3) Place of performance
      Nuts code:
      UK - UNITED KINGDOM
   
      Main site or place of performance:
      UNITED KINGDOM
             

      II.2.4) Description of the procurement: The Contractor is required to act as a design and build contractor and will be responsible for all civil, mechanical, electrical construction; installation and commissioning of the following – but not limited to - within the CDM Works area (i.e., The R80 roof area) and in accordance with the Completion Dates (See Provisional Programme within Appendix D - Project Brief). - 8 No New Adiabatic coolers (AC’s). - Connecting pipework and fittings to and the new AC’s within the CDM Works Area. - All types of valves (isolation, regulating, non-return either manual or actuated). - Commissioning sets and pressure reducing valves. - Testing and drainage points. - Basket and other Filters. - All steel support work for the Adiabatic Coolers. - All pipework supports. - All local electrical power and signal cabling with cable trays etc and supports. - All necessary civil surveying /setting out work. The Contractor will be entirely responsible for organising the decommissioning and removal of the existing Balticare Cooling Towers within the CDM Works Area. Background The ISIS Neutron and Muon Source is a world-leading centre for research at the STFC Rutherford Appleton Laboratory near Oxford. The R80 facility houses the Second Target Station (TS2) and its associated neutron beamlines. At the end of each beam line is an instrument hut complete with research instrumentation all of which require a source of suitably graded cold demineralised water. The Demin cooling water used to cool the target is provided by a ‘closed loop’ circuit with the duty/standby pump arrangement; two Plate Heat Exchangers (PHExs) and associated controls situated within the Level 2 West Plant Area T222. Likewise, the instrument water is fed from a similar set up situated within the Level 2 West Plant Area T220 on the same storey. A source of cooling is also necessary for the focusing magnets and associated power supplies along the main proton beamline that leads to TS2 - known as the Extract Proton Beamline 2 or EPB2. The R6 Plant link room – situated in the corridor that links the R6 facility to R80 – houses the EPB2 Magnet Demin cooling water system and a separate power supplies Demin circuit. All the above ‘closed loop’ water circuits contain a ‘coarse’ grade cooling PHEx that uses the process water (PW) and a PHEx fed with chilled water (CHW) used to ‘trim’ each circuit Demin to the required Semin water supply temperature. Currently the process water circuit is a ‘closed circuit’ system comprising of 5 No Balticare (BAC) VX1-180-4+XB towers each rated at 800 kW. These towers are located on the R80 4th floor roof. Adjacent to the roof area leading to the first two towers is the R80 Chilled Water Plant room (Level 4 West plant room T410) which houses both the duty/standby process water pumps and 3 No TRANE 850 kW R134a charged RTHD C2 D5 E4 Chillers which are water cooled using the PW. Flow is maintained through the packaged chillers and primary loop header system by duty/standby chilled water pumps located within the Level 2 West plan room T222 together with the target circuit. Besides providing cooling to the different CHW PHExs mentioned above the chilled water system also provides substantial space cooling via Fan Coil Units (FCUs) situated in the R80 office; laboratories; server and control rooms. The water circuits were originally designed and installed by HADEN-YOUNG during the original construction phase of the R80 facility in 2006.

      II.2.5) Award criteria:
       Not Provided

      II.2.11) Information about options
         Options: No
         

      II.2.13) Information about European Union funds
         The procurement is related to a project and/or programme financed by European Union funds: No
         

      II.2.14) Additional information: Additional information: We strongly recommend that you attend the Site Tour in order to gain complete clarity of our requirements. Please follow the instructions within the ITT.


Section IV: Procedure

IV.1) Description

   IV.1.1)Type of procedure: Open


   IV.1.3) Information about a framework agreement or a dynamic purchasing system
      The procurement involves the establishment of a framework agreement: No       
      

   IV.1.6) Information about electronic auction
      An electronic auction has been used: No

   IV.1.8) Information about the Government Procurement Agreement (GPA)
      The procurement is covered by the Government Procurement Agreement: Yes

IV.2) Administrative information

   IV.2.1) Previous publication concerning this procedure
       Notice number in the OJEU: 2022/S 000-022510
      
   

   IV.2.9) Information about termination of call for competition in the form of a prior information notice
      The contracting authority will not award any further contracts based on the above prior information notice: No

Section V: Award of contract

Award Of Contract (No.1)

   Contract No: UKRI-2253    
   Lot Number: Not Provided    
   Title: UKRI-2253 R80 Tower Decommissioning and Adiabatic Cooler Design and Build

   A contract/lot is awarded: Yes


   V.2) Award of contract

      V.2.1) Date of conclusion of the contract: 14/12/2022

      V.2.2) Information about tenders
         Number of tenders received: 5
         Number of tenders received from SMEs: Not Provided          
         Number of tenders received from tenderers from other EU Member States: Not Provided          
         Number of tenders received from tenderers from non-EU Member States: Not Provided          
         Number of tenders received by electronic means: Not Provided

      V.2.3) Name and address of the contractor

      The contract has been awarded to a group of economic operators: No
         
         Contractor (No.1)
             Vistech Cooling Systems Ltd, 04808079
             Vistech Cooling Systems Ltd,, Unit 1 A, Church Lane Estate, Church Lane,, Horsham, RH13 6LU, United Kingdom
             NUTS Code: UK
            The contractor is an SME: Yes

      V.2.4) Information on value of the contract/lot (excluding VAT)
         Initial estimated total value of the contract/lot: Not Provided          
         Total value of the contract/lot: 1,507,366
         Currency: GBP

      V.2.5) Information about subcontracting
         The contract is likely to be subcontracted: No
         
Section VI: Complementary information

   VI.3) Additional information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.
To view this notice, please click here:
https://ukri.delta-esourcing.com/delta/viewNotice.html?noticeId=745369639

   VI.4) Procedures for review

      VI.4.1) Review body
          UK Research and Innovation
          Swindon, United Kingdom

      VI.4.3) Review procedure
         Precise information on deadline(s) for review procedures: Not Provided

      VI.4.4) Service from which information about the review procedure may be obtained
         Not Provided

   VI.5) Date of dispatch of this notice: 19/12/2022